Who can also agree on the project being completed?

Prepare for the PMI GMetrix Test with comprehensive quizzes. Utilize flashcards, practice multiple choice questions, and study detailed explanations to excel in your exam. Elevate your confidence and get exam ready today!

Multiple Choice

Who can also agree on the project being completed?

Explanation:
Formal completion of a project is approved by the person who holds the authority to close the project and accept the final deliverables—the project sponsor. The sponsor oversees the business case, funding, and benefits realization, so their sign-off confirms that objectives are met and the project can close, resources can be released, and the intended benefits can proceed. The customer may also accept the deliverables, but the sponsor is the one with the formal authority to declare completion in governance terms. The project manager runs the work and orchestrates closeout, but cannot unilaterally finalize the project’s status. General managers don’t automatically have that project-specific sign-off authority.

Formal completion of a project is approved by the person who holds the authority to close the project and accept the final deliverables—the project sponsor. The sponsor oversees the business case, funding, and benefits realization, so their sign-off confirms that objectives are met and the project can close, resources can be released, and the intended benefits can proceed. The customer may also accept the deliverables, but the sponsor is the one with the formal authority to declare completion in governance terms. The project manager runs the work and orchestrates closeout, but cannot unilaterally finalize the project’s status. General managers don’t automatically have that project-specific sign-off authority.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy