When does a scope change occur?

Prepare for the PMI GMetrix Test with comprehensive quizzes. Utilize flashcards, practice multiple choice questions, and study detailed explanations to excel in your exam. Elevate your confidence and get exam ready today!

Multiple Choice

When does a scope change occur?

Explanation:
Scope changes only become real when they’ve gone through formal change control and been approved. A change request is raised to alter scope, then evaluated for its impact on scope, schedule, cost, and risk. If the Change Control Board (or the designated authority) approves it, the project’s baselines are updated and the change is implemented. If it isn’t approved, the current scope stays as is. This is why the timing of a scope change is after approval, not before or during initiation or closeout.

Scope changes only become real when they’ve gone through formal change control and been approved. A change request is raised to alter scope, then evaluated for its impact on scope, schedule, cost, and risk. If the Change Control Board (or the designated authority) approves it, the project’s baselines are updated and the change is implemented. If it isn’t approved, the current scope stays as is. This is why the timing of a scope change is after approval, not before or during initiation or closeout.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy