Should the project scope, schedule, and budget be adjusted as the project has reached its closing phase?

Prepare for the PMI GMetrix Test with comprehensive quizzes. Utilize flashcards, practice multiple choice questions, and study detailed explanations to excel in your exam. Elevate your confidence and get exam ready today!

Multiple Choice

Should the project scope, schedule, and budget be adjusted as the project has reached its closing phase?

Explanation:
In the closing phase, the focus is on confirming completion, obtaining formal acceptance, and documenting final outcomes. The baseline values for scope, schedule, and budget are the references used during execution to measure performance, not something you keep changing at the end. By the time you close a project, you verify what was delivered, capture final actuals, and record variances for archival purposes. If any change requests were approved, their impacts should already be reflected in the final records; outstanding change requests would have been resolved before closing. So you don’t adjust the scope, schedule, or budget simply to reflect that the project is finishing.

In the closing phase, the focus is on confirming completion, obtaining formal acceptance, and documenting final outcomes. The baseline values for scope, schedule, and budget are the references used during execution to measure performance, not something you keep changing at the end. By the time you close a project, you verify what was delivered, capture final actuals, and record variances for archival purposes. If any change requests were approved, their impacts should already be reflected in the final records; outstanding change requests would have been resolved before closing. So you don’t adjust the scope, schedule, or budget simply to reflect that the project is finishing.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy