In which phase are project goals defined and initial authorization obtained?

Prepare for the PMI GMetrix Test with comprehensive quizzes. Utilize flashcards, practice multiple choice questions, and study detailed explanations to excel in your exam. Elevate your confidence and get exam ready today!

Multiple Choice

In which phase are project goals defined and initial authorization obtained?

Explanation:
Initiating phase. This stage creates the project charter, which states the project’s high-level objectives and grants the project manager the authority to use organizational resources. Defining these initial goals and securing formal authorization to proceed happen here, before planning in detail. After this, planning develops the specifics of how to achieve the goals, while executing carries out the work and closing wraps things up.

Initiating phase. This stage creates the project charter, which states the project’s high-level objectives and grants the project manager the authority to use organizational resources. Defining these initial goals and securing formal authorization to proceed happen here, before planning in detail. After this, planning develops the specifics of how to achieve the goals, while executing carries out the work and closing wraps things up.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy