In a WBS, which element is at the lowest level where cost and duration are managed?

Prepare for the PMI GMetrix Test with comprehensive quizzes. Utilize flashcards, practice multiple choice questions, and study detailed explanations to excel in your exam. Elevate your confidence and get exam ready today!

Multiple Choice

In a WBS, which element is at the lowest level where cost and duration are managed?

Explanation:
In a WBS, you break the project scope into progressively smaller pieces until you reach units that you can plan and control effectively. The smallest unit designed for this purpose is the work package. A work package is where you attach the cost estimate and the duration, and where progress can be measured and managed. Deliverables are outputs produced by combining several work packages; activities and tasks are elements used in the scheduling view to show the sequence and timing of work, but they aren’t the lowest WBS elements that carry cost and duration in the control process. That’s why the bottom-level element in the WBS, the work package (often referred to simply as work), is the place where cost and duration are managed.

In a WBS, you break the project scope into progressively smaller pieces until you reach units that you can plan and control effectively. The smallest unit designed for this purpose is the work package. A work package is where you attach the cost estimate and the duration, and where progress can be measured and managed. Deliverables are outputs produced by combining several work packages; activities and tasks are elements used in the scheduling view to show the sequence and timing of work, but they aren’t the lowest WBS elements that carry cost and duration in the control process. That’s why the bottom-level element in the WBS, the work package (often referred to simply as work), is the place where cost and duration are managed.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy