Finish-finish dependency in scheduling means:

Prepare for the PMI GMetrix Test with comprehensive quizzes. Utilize flashcards, practice multiple choice questions, and study detailed explanations to excel in your exam. Elevate your confidence and get exam ready today!

Multiple Choice

Finish-finish dependency in scheduling means:

Explanation:
Finish-finish dependencies connect the completion moments of two activities. The requirement is that the finish of one task occurs before the finish of the other task. This means one task cannot be completed until the first has already finished, tying their finish times together. It’s different from other dependency types that link when activities start in relation to finishes or starts of others (for example, a task starting after another finishes, or two tasks starting in tandem). In finish-finish, the emphasis is on the order of completions rather than the starts.

Finish-finish dependencies connect the completion moments of two activities. The requirement is that the finish of one task occurs before the finish of the other task. This means one task cannot be completed until the first has already finished, tying their finish times together. It’s different from other dependency types that link when activities start in relation to finishes or starts of others (for example, a task starting after another finishes, or two tasks starting in tandem). In finish-finish, the emphasis is on the order of completions rather than the starts.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy